KIR 13th Fantrie_Public EN operation : Progress Report

Klaytn Improvement Reserve: Progress Report

Summary

  • Pretty much well-operated with no trouble.
  • Both data transfer and labor costs got much higher than expected, thus node operational costs need to be raised.

Project Milestones and Schedule

Currently managin 5 End Point Nodes.

Key Deliverables

  1. Providing Stable public EN nodes
  2. Keeping the failure time within 10 minutes per month

Budget

refer to attachment.

attachment

The budget increase requested in this progress report has been confirmed by GCs and will be reflected in next budget execution.